Caltrans Logo

Widen Ramp For Deceleration Lane

Description: In the city of Irvine, on northbound Route 405 from 1 mile north of Jeffery Road Overcrossing to Culver Drive Overcrossing. Widen Ramp For Deceleration Lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Irvine
Zip Code 92614
 
Senate District
35
Assembly District 70
Congressional District 47
 
Caltrans District
12
 
 
County/State Route Orange 405
Postmile Begin/End 5 5.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      415  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0.24  
Peak Period Time Savings (minutes)      33,020  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Bob Bazargan (949)724-2100   bob_bazargan@dot.ca.gov
Design (PS&E) Phase
Caltrans Benjamin Ionescu (949)724-2892   Benjamin_Ionescu@dot.ca.gov
Right of Way Phase
Caltrans Bob Bazargan (949)724-2100   bob_bazargan@dot.ca.gov
Construction Phase
Caltrans Krystal Merkwan (714)558-4402   Merkwan, Krystal R@DOT
 
Corridor System Management Plan
Caltrans Bob Bazargan (949)724-2100   bob_bazargan@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$2,410 $-172 $2,238
Non-bond Funding
State/Federal*
$820 $0 $820
 
Total**** $3,230 $-172 $3,058

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$155 $0 $155 $154
Design(PS&E)
$665 $0 $665 $701
Right of Way
$0 $0 $0 $1
Construction
$2,410 $-172 $2,238 $2,236
 
Total* $3,230 $-172 $3,058 $3,092

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/15/2011 

03/21/2012 
 

 
04/15/2011 

03/21/2012 
100   

03/21/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/15/2011 

06/20/2012 
 

 
04/15/2011 

06/20/2012 
100   

06/06/2012 


Begin Right of Way Phase

End Right of Way Phase
09/15/2011 

05/31/2012 
 

 
09/15/2011 

05/31/2012 
100   

 


Begin Construction Phase

End Construction Phase
12/01/2012 

07/01/2014 
 

 
12/01/2012 

07/01/2014 
100  10/11/2012 

05/30/2014 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

12/01/2014 
 

 
07/01/2014 

12/01/2014 
100  01/10/2014 

12/01/2014 


Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 415
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0.24
Peak Period Time Savings (minutes) 33,020

Bond Funding Cost
Adopted:
$2,410,000
Current Approved:
$820,000
Actual Expenditures:
$856,000

 

Status as of December 31, 2023.