Widen Ramp For Deceleration Lane |
Description: In the city of Irvine, on northbound Route 405 from 1 mile north of Jeffery Road Overcrossing to Culver Drive Overcrossing. Widen Ramp For Deceleration Lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Irvine |
Zip Code | 92614 |
Senate District |
35 |
Assembly District | 70 |
Congressional District | 47 |
Caltrans District |
12 |
County/State Route | Orange 405 |
Postmile Begin/End | 5 5.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 415 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0.24 | |
Peak Period Time Savings (minutes) | 33,020 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Bob Bazargan | (949)724-2100 | bob_bazargan@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Benjamin Ionescu | (949)724-2892 | Benjamin_Ionescu@dot.ca.gov | |
Right of Way Phase |
Caltrans | Bob Bazargan | (949)724-2100 | bob_bazargan@dot.ca.gov | |
Construction Phase |
Caltrans | Krystal Merkwan | (714)558-4402 | Merkwan, Krystal R@DOT | |
Corridor System Management Plan |
Caltrans | Bob Bazargan | (949)724-2100 | bob_bazargan@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$2,410 | $-172 | $2,238 | ||||
Non-bond Funding | |||||||
State/Federal* |
$820 | $0 | $820 | ||||
Total**** | $3,230 | $-172 | $3,058 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$155 | $0 | $155 | $154 | |||
Design(PS&E) |
$665 | $0 | $665 | $701 | |||
Right of Way |
$0 | $0 | $0 | $1 | |||
Construction |
$2,410 | $-172 | $2,238 | $2,236 | |||
Total* | $3,230 | $-172 | $3,058 | $3,092 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
04/15/2011 03/21/2012 |
|
04/15/2011 03/21/2012 |
100 | 03/21/2012 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/15/2011 06/20/2012 |
|
04/15/2011 06/20/2012 |
100 | 06/06/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/15/2011 05/31/2012 |
|
09/15/2011 05/31/2012 |
100 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/01/2012 07/01/2014 |
|
12/01/2012 07/01/2014 |
100 | 10/11/2012 05/30/2014 |
2 1 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2014 12/01/2014 |
|
07/01/2014 12/01/2014 |
100 | 01/10/2014 12/01/2014 |
6 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 415 | |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0.24 | |
Peak Period Time Savings (minutes) | 33,020 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,410,000 |
Current Approved: |
$820,000 |
Actual Expenditures: |
$856,000 |
Status as of December 31, 2023.